CURRENTRFQ- Construction Manager at Risk (CMAR) Services Submittals Due: March 13, 2026 |
Questions for Review:
Q: How far into the process have the architect and civil engineer progressed?
A: The architect has completed Schematic Design and anticipates completing Design Development phase on or before April 20. The civil engineer is actively working towards their permit documents.
Q: How many different design phase prices are you estimating will be required during the Pre-Construction phase?
A: Please budget for a full estimate on the Design Development package. The project schedule will not afford time for any other interim estimates prior to final GMP bidding, so the expectation from the selected Construction Manager is to provide sufficient guidance from the DD estimate for the owner and design team to make the required adjustments to align the GMP with the owner's construction budget.
Q: The project description mentions this being the first phase. Will this phase include site development of the entire 11 acres or only the portion of it that the proposed building is on and the agency requirements for stormwater?
A: Please see the attached site plan for a better understanding of the proposed conceptual site development plan. The design includes space accommodations for some future buildings or structures. Final grading and utility plans have not yet been developed.
Q: How far into the process have the architect and civil engineer progressed?
A: The architect has completed Schematic Design and anticipates completing Design Development phase on or before April 20. The civil engineer is actively working towards their permit documents.
Q: How many different design phase prices are you estimating will be required during the Pre-Construction phase?
A: Please budget for a full estimate on the Design Development package. The project schedule will not afford time for any other interim estimates prior to final GMP bidding, so the expectation from the selected Construction Manager is to provide sufficient guidance from the DD estimate for the owner and design team to make the required adjustments to align the GMP with the owner's construction budget.
Q: The project description mentions this being the first phase. Will this phase include site development of the entire 11 acres or only the portion of it that the proposed building is on and the agency requirements for stormwater?
A: Please see the attached site plan for a better understanding of the proposed conceptual site development plan. The design includes space accommodations for some future buildings or structures. Final grading and utility plans have not yet been developed.